Precision Specialized to tackle most challenging oversize load yet

BURLINGTON, Ont. – It’s a move so long and complex, nothing is being left to chance. Even a mobile washroom is being taken along. Yet, the pickup and delivery locations are only about 17 kilometers apart, as the crow flies.

For Precision Specialized, the 108-km journey begins Sept. 28 for what will be “by far the most complex, biggest, most difficult thing we’ve ever done,” company president Ed Bernard told Today’s Trucking.

(Photo: Precision Specialized)

Seven loads will be moved in a convoy over five nights, ranging in weight from 260,000 to 320,000 lbs, with overall dimensions of up to 125’ long, 26’ wide, and 24’4” high. The power generation modules are being transported from manufacturer Zeton’s Oakville, Ont., plant to the Port of Hamilton. From there they’ll be shipped to a customer overseas, but Precision Specialized’s work will be done once they reach the port.

It has taken nearly two years to plan the delivery. In fact, Bernard said he began making arrangements even before Zeton committed to the project to help the manufacturer determine if the job was viable.

“We did the feasibility studies before the manufacturer even decided to accept the job,” he said, adding it was rewarding to help a local supplier obtain work.

There will be eight loads in total, including the seven in the convoy. The smaller eighth load can travel on the highway. More than 70 subcontractors have been enlisted to help. The oddest requirement was the mobile toilet, since the route will take those 70 people as far off the beaten path as possible, late at night to minimize the disruption to traffic and residents.

Because of the height of the loads, power lines will have to be lifted, cutting power to nearby houses. Residents have been notified and Precision is putting out the word of the move so motorists can avoid the route and its associated rolling road closures.

Other subcontractors coming along for the trip include bucket utility truck operators, police, superload escorts, a mobile mechanic, a spare tractor and two spare escorts, a tire truck, and even a food truck.

The biggest risk in a job of this magnitude, said Bernard, is falling behind schedule.

“There are a lot of moving parts,” he explained. “A lot of people will lose their power and we want to make sure we keep to our schedule.”

(Source: Precision Specialized)

Weather is also a risk – even rain can cause delays.

And then there’s the Covid-19 pandemic to throw a wrench in things. While those working on the project won’t be closely congregated, precautions have been taken at planning meetings such as temperature checks, masks and social distancing. Once the move starts, Bernard likens the work environment to a “quarter mile bubble that’s traveling and that you can’t get into.”

The drivers are all seasoned professionals when it comes to hauling oversize loads, and most relish the challenge, Bernard said.

“All our guys have pulled big before,” he said. “This is a little beyond. We have pulled over 20-ft wide, but the height of the combination we have is kind of new for us, as is the shear scope and scale. They’re well trained and experienced and all have done this in one way, shape, or form.”

Nightly road closures

There will be short-duration rolling road closures during the move, between the hours of 10 p.m. and 5 a.m. Here are the roads affected:

Night 1: Sept. 28-29

  • Michigan Drive East
  • Burloak Drive North
  • North Service Road West
  • Brant Street North
  • Dundas Street (Hwy. 5) West
  • Avonsyde Boulevard north
  • Parkside Drive West @ Clappison Avenue

Night 2: Sept. 29-30

  • Parkside Drive West @ Clappison Avenue
  • Hwy. 6 North
  • Regional Road 97 West @ Foreman Road

Night 3: Sept. 30-Oct. 1

  • Regional Road 97 West @ Foreman Road
  • Kirkwall Road South
  • Hwy. 8 South/East
  • Hwy. 52 South/East @ Wilson Street

Night 4: Oct. 1-2

  • Hwy. 52 South/East
  • Carluke Road (Road 65) East
  • Upper James Street north
  • Rymal Road East
  • Centennial Parkway (Hwy. 20) North @ Mud Road

Night 5: Oct. 2-3

  • Centennial Parkway (Hwy. 20) North @ Mud Road
  • Barton Street West
  • Wentworth Street North
  • Burlington Street West
  • Wilfred Street North
Avatar photo

James Menzies is editorial director of Today's Trucking and TruckNews.com. He has been covering the Canadian trucking industry for more than 24 years and holds a CDL. Reach him at james@newcom.ca or follow him on Twitter at @JamesMenzies.


Have your say


This is a moderated forum. Comments will no longer be published unless they are accompanied by a first and last name and a verifiable email address. (Today's Trucking will not publish or share the email address.) Profane language and content deemed to be libelous, racist, or threatening in nature will not be published under any circumstances.

*

  • Empire Transportation has been moving loads like that for years untill people started cutting all the profit out of the loads.

  • Not to detract from what they are doing – Ontario is its own special challenge for anything oversize – but these dimensions move daily in many other jurisdictions. With all of the press surrounding these loads, one expects really big loads, until reading the article and seeing the actual dimensions.

    Being from Alberta, it was normal to see a dozen loads like this in a day, when things were busy.

  • I drive past their yard and see them setting up trailers. Very interesting.
    I would imagine people will curse this load the same way most curse a combine travelling down the road. “This thing is blocking the way I want to go”!
    Small inconvenience so someone else can make a living.
    Many hate it, I think that it’s an awesome piece of machinery!

  • How is the supper move going??
    I would like to see the units parked for the day. Are the seven units still on the planed schedule?????
    Thanks Dan

  • Wow! Kudo’s to the Precision team for pulling this off. This is very impressive in the world of specialized heavy haul there are not that many you can work with in Ontario.

    I will definitely be getting Precision to quote on our projects.